We just received the latest update regarding the Cyril Ross Nursery Renovation Project.
Below is the progress report from the project contractor Damion Marcellin
Date: 14th Febuary, 2012
Site: Cyril Ross Nursery Eldorado Rd
Project: Renovation of Pharmacy and Isolation Room
Contractor: DAMYK LTD
Work completed to date are as follows
Pharmacy
- Foundation beams casted (09/02/2012)
- Slab casted (11/02/2012)
- Exterior wall erected (12/02/2012)
- Exterior wall plastered (14/02/2012)
- Started framing of ceiling behind doctor’s office (13/02/2012)
- Electrical wiring has started for lights and plugs in the pharmacy (14/02/2012)
- Emergency gate removed and relocated to the front (13/02/2012)
- Door on the corridor to the pharmacy changed (13/02/2012)
- Removal of waste material and rubble from site (14/02/2012)
Isolation Room
- Wall erected to separate rooms (09/02/2012)
- Bathroom floor tiled (11/02/2012)
- Entrance door changed (13/02/2012)
- Old window removed
- Door framed installed and blocks erected for bath room (14/02/2012)
- Electrical for air conditioning unit completed (14/02/2012)
Work to be completed by 18th Febuary, 2012 as weather permits
- Repair roof over doctor’s office
- Cover extension over pharmacy
- Demolition of old pharmacy wall
- Installation of air condition in pharmacy
- Installation of air condition in isolation room
- Cast ring beam for roof (15/02/2012)
Thank you,
Damion Marcelllin Contractor